At long last, the Liberian government will break grounds for the reconstruction of the Mount Coffee Hydro Power-Plant, a flagship project of President Johnson Sirleaf.

The hydro reconstruction is part of an aggressive government program to redevelop the country’s energy sector, shattered by prolonged civil and political unrest.

President Johnson Sirleaf is expected to lead an array of government officials, and donor partners to the ground breaking for civil works construction tomorrow Saturday, January 25, 2014.

With the hydro generating 80megawatt during the raining season, the government has indicated that current cost of electricity at $ 0.54 per kilowatt hour would be reduced by half.

Sometime last year, Finance Minister Amara Konneh announced that the Liberian government had mobilized close to 1.2 billion dollar to support  infrastructure projects – such as the Mount Coffee hydro-plant which is expected to increase power supply for Liberia.

“We want to extend the energy supply to households and businesses and across the whole country. To this end we are working with our development partners, the Japanese Government and World Bank, to build three power plants over the next 2 years, for a total of 38MW. Out of the 38MW capacity, the18MW is being financed through our budget,” he said.

The Mount Coffee Hydro Electric Power Plant, which is co-financed by the Governments of Liberia, Norway and Germany, in partnership with the European Investment Bank (EIB) and the World Bank, should see power capacity jump to 80MW once completed. The government share of the financing is US $ 47 million dollars, reports say.

According to the government’s energy strategy, it also  intends to subscribe to the regional power plan – West African Power Pool (WAPP) that will create an integrated grid among Cote d’Ivoire, Liberia, Sierra-Leone & Guinea (CLSG), costing an estimated $415 million, while US$202 million will be spent on Liberia in an effort to link Yekepa, Buchanan, and  Mt Coffee.

This project is also being supported by the Liberian Government, World Bank, AfDB, & Germany and  a separate $14 million EU cross-border project which is expected to electrify Nimba, Grand Gedeh and Maryland.  Courtesy Heritage Newspaper, with edits by Ralph Geeplay